First Appellate District, Case No. A113376
[San Mateo Superior Court Case No. 444270]
In The Court of Appeal, State of California
FIRST APPELLATE DISTRICT
DIVISION THREE
_________________
UPHOLD
OUR HERITAGE
Plaintiff
and Respondent,
vs.
TOWN
OF WOODSIDE,
Defendant
and Appellant,
STEVEN
JOBS,
Real
Party in Interest and Appellant
_________________
Appeal
From the Superior Court for the County of San Mateo,
The
Honorable Marie S. Weiner,
Granting
Petition for Writ of Mandate
_________________
RESPONDENTÕS
OPPOSITION BRIEF
____________
Chatten-Brown & Carstens
Jan Chatten-Brown (Bar No. 50275)
Douglas P. Carstens (Bar No. 193439)
3250 Ocean Park Boulevard, Suite 300
Santa Monica, California 90405-3219
Telephone:
(310) 314-8040
Attorneys for Respondent Uphold Our Heritage
TABLE OF
CONTENTS
pAGE NO.
INTRODUCTION ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ... 1
statement OF FACTS ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ.. 3
I. THE HISTORICAL SIGNIFICANCE OF THE JACKLING HOUSE ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ. 3
II. OWNERSHIP AND USAGE OF THE JACKLING HOUSE. ÉÉ 4
III. DEMOLITION PERMIT
APPLICATION AND REVIEW ÉÉÉ 4
I. Woodside Violated CEQA by Approving Demolition
of a Significant Historical Structure Without SuBSTANTIAL Evidence of
Infeasibility of Alternatives ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ.. 11
A. CEQAÕs Substantive Mandates Encompass Historical Resources and Denial of a Project is Required When There Is a Feasible Alternative ÉÉÉÉÉÉÉÉÉÉÉÉÉÉ 11
b. Evidence About the Cost of the Demolition and Construction Project Does Not Support the Finding of Infeasibility of All Alternatives ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ.. 14
1. The Amount of Money Required for Preservation Alternatives, Without Context, is Insufficient to Show Infeasibility ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ... 15
a. Information About the Full Scope of the Project Was Required to Provide Context ÉÉÉÉ. 16
b. Consideration of Context is Required Because the Costs of Mitigation Vary With a ProjectÕs Impacts ÉÉÉÉÉÉÉÉÉÉÉÉÉÉ.. 17
c. AppellantsÕ Cases are Inopposite because those Cases Included an Economic Analysis ÉÉ.. 18
2. Evidence about the Financial Resources of the Project Applicant Conflicts with the Finding of
Infeasibility ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ... 22
3. Evidence about Possible Outside Funding Sources Conflicts with the Finding of Infeasibility of the Relocation Alternative ÉÉÉÉÉÉÉÉÉÉÉ.. 23
4. JobsÕ Opposition to Alternatives is not Substantial Evidence that they Are Infeasible ÉÉÉÉÉÉÉ. 26
C. Conditioning
the Grant of a Demolition Permit on Implementation of Preservation or
Relocation Alternatives Was Not ÒLegally InfeasibleÓ ÉÉÉÉÉÉÉÉÉÉÉ.. 30
1. Woodside Had Discretion to Deny the Demolition Project ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ... 30
2. No Statute, Guideline, or Constitutional Provision Prohibits Imposing Conditions on Approval of Demolition. ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ... 32
3. Denial of a Demolition Permit Is Not the Same as Imposing an Affirmative Obligation to Preserve the House ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ 34
II.
WOODSIDEÕS Statement of Overriding Considerations is Not
supported by substantial evidence ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ 35
A. CEQA Requires Specific Findings Supported by Substantial
Evidence for Any Statement of Overriding
Considerations ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ. 35
B. WoodsideÕs General Plan Supports Preservation, Not
Demolition, of Historic Resources ÉÉÉÉÉÉÉÉÉ.. 37
C. WoodsideÕs Conditions of Approval Do Not Convey a Benefit Supporting Demolition ÉÉÉÉÉÉÉÉÉÉ... 41
III. THE Findings OF Infeasibility and Overriding Considerations FAIL TO Disclose WOODSIDEÕS Analytic Route ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ. 43
IV. THE PERMIT MUST BE SET ASIDE ÉÉÉÉÉÉÉÉÉÉ. 44
CONCLUSION ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ. 47
table of authorities
Page no(s).
STATE CASES
Association of Irritated Residents v. County of Madera (ÒAIRÓ),
(2003) 107
Cal.App.4th 1383 ÉÉÉÉÉÉÉÉÉÉÉÉÉ 27,
31
Berkeley Keep Jets Over the Bay Com. v. Board of Port Cmrs.
(2001) 91 Cal.App.4th 1344ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ
42
Cadiz Land Co., Inc. v. Rail Cycle, L.P.
(2000) 83 Cal.App.4th 74 ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ... 17
Citizens of Goleta Valley v. Board of Supervisors (ÒGoleta IÓ)
(1988) 197 Cal.App.3d 1167 ÉÉÉÉÉÉÉÉÉÉ. 14, 29, 45
Citizens for Quality Growth v. City of Mt. Shasta
(1988) 198 Cal.App.3d 433 ÉÉÉÉÉÉÉÉÉÉÉÉÉÉ.... 36
City of Fremont v. San Francisco Bay Area Transit District
(1995) 34 Cal.App.4th 1780 ÉÉÉÉÉÉÉÉÉÉÉÉÉ.. 15, 19
Cleary v. County of Stanislaus
(1981) 118 Cal.App.3d 348 ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ 36
County of San Diego v. Grossmont-Cuyamaca Community College District
(2006) Ð Cal.App.-- ÉÉÉÉÉÉÉÉÉÉÉ É.ÉÉ12, 13, 37
Dusek v. Redevelopment Agency
(1985) 173 Cal.App.3d 1029 É.ÉÉÉÉÉÉÉÉÉÉÉÉÉ. 40
Environmental
Protection Information Center, Inc.
v. Johnson
(1985) 170 Cal.App.3d 604 .ÉÉÉÉÉÉÉÉÉÉÉÉÉÉ... 46
Families
Unafraid to Uphold Rural Etc. County v. Board of Supervisors
(1998)
62 Cal.App.4th 1332 ÉÉÉÉÉÉÉÉÉÉÉÉÉÉ.
39
First Presbyterian Church of Berkeley v. City of Berkeley
(1997) 59 Cal.App.4th 1241 ÉÉÉÉÉÉÉÉÉÉÉÉÉÉ... 30
Friends
of the Eel River v. Sonoma County Water Agency
(2003) 108 Cal.App.4th 859 ÉÉÉÉÉÉÉÉÉÉÉÉÉ. 42, 45
Friends of Sierra Madre v.
City of Sierra Madre
(2001) 25 Cal.4th 165 ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ 13
Friends of Westwood, Inc. v. City of Los Angeles
(1987) 191 Cal.App.3d 259 ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ 30
Foundation for San
FranciscoÕs Architectural Heritage v. City and County
of San Francisco (1980) 106 Cal.App.3d 893 ÉÉÉ.. 21, 27, 28, 43
Greenbaum v. City of Los Angeles
(1984) 153 Cal.App.3d 391 ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ 29
Kings County Farm Bureau
v. City of Hanford
(1990) 221
Cal.App.3d 692 .....ÉÉÉÉÉÉÉÉÉÉÉÉÉ... 28
Koster
v. County of San Joaquin
(1996) 47 Cal.App.4th 29 ÉÉÉÉÉÉÉ.ÉÉÉÉÉÉÉ. 7 fn 2
Laurel Heights Improvement Assoc. v. Regents
of University of California
(ÒLaurel Heights IÓ) (1988)
47 Cal.3d 376 ÉÉÉÉÉ.É. 2 fn1, 43
Lincoln Place Tenants
Ass'n v. City of Los Angeles
(2005) 130 Cal.App.4th 1491 ÉÉÉÉÉÉÉÉÉÉ 13, 15, 16
Los Angeles Unified School
Dist. v. City of Los Angeles
(1997) 58 Cal.App.4th 1019 ÉÉÉÉÉÉÉÉÉÉÉÉ 17, 35
Maintain Our Desert Environment v. Town of Apple Valley (ÒMODEÓ)
(2004) 124 Cal.App.4th 430 ÉÉÉÉÉÉÉÉÉÉÉ 15, 22, 23
No
Oil, Inc. v. City of Los Angeles
(1974) 13 Cal.3d 68 ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ .. 45
No Slo Transit v. City of Long Beach
(1987) 197 Cal.App.3d 241 ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ 29
People
v. County of Kern
(1974) 39
Cal.App.3d 830 ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ. 46
Pocket Protectors v.
City of Sacramento
(2004) 124 Cal.App.4th
903 ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ 26
Prentiss v. City of South Pasadena
(1993) 15 Cal.App.4th 85 ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ 30
Resource Defense Fund v. Local Agency Formation Com.
(1987) 191 Cal.App.3d 886 ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ 36
San Franciscans Upholding
the Downtown Plan v. City and County of San
Francisco (2002) 102 Cal.App.4th 656 ÉÉÉÉÉÉÉ... 15, 18, 27
Sequoyah Hills Homeowners Assn. v. City of Oakland
(1994) 23 Cal.App.4th 704 ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ.. 31
Sierra Club v. County of
Contra Costa
(1992) 10 Cal.App.4th 1212 ÉÉÉÉÉÉÉÉÉÉÉÉ..... 35, 40
Sierra Club v. County of
Napa
(2004) 121 Cal.App.4th 1490 ÉÉÉÉÉÉÉÉÉÉÉÉ.. 27, 46
Sierra Club v. Gilroy City
Council
(1990) 222 Cal.App.3d 30 ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ.. 12
Topanga Assn. for a Scenic Community v. County of Los Angeles
(1974) 11
Cal. 3d 506 ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ. 43
Village Laguna of Laguna
Beach v. Board of Supervisors of Orange County
(1982)
134 Cal.App.3d 1022 ÉÉÉÉÉÉÉÉ... 17-18, 35, 36, 43
FEDERAL CASES
Benenson v. United States
(1977) 548 F.2d 939 ÉÉÉÉÉÉÉÉÉÉÉÉÉÉ.. 33, 34 fn 6
Penn Cent. Transp. Co. v.
City of New York
(1978) 438 U.S. 104 ÉÉÉÉÉÉÉÉÉÉÉÉÉÉ... 32, 34, 40
Tahoe-Sierra Preservation Council, Inc. v. Tahoe Regional Planning Agency (2002) 535 U.S. 302 ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ.. 33 fn 5
OTHER CASES
State, By Powderly v.
Erickson
(Minn. 1981) 301 N.W. 2d 324 ÉÉÉÉÉÉÉÉÉÉÉÉÉ. 32
PUBLIC RESOURCES CODE
Section 5020.4 (a)(8) ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ... 8, 9
Section 5024.1 (a) ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ 8, 9
Section 21001 subd.(c) ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ.. 13
Section 21002 ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ 1, 12
Section 21002.1 ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ. 1, 12
Section 21004 ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ 31
Section 21061.1 ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ... 2, 12, 27
Section 21081
ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ.. 1, 35, 43
Section 21084.1 ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ. 13
Section 21167.2 ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ. 45
CEQA Guidelines Section
15093 (b) ÉÉÉÉÉÉÉÉÉÉÉÉÉÉ 37
Government Code Section 65589.5 subd. (j)(1) ÉÉÉÉÉÉÉÉÉÉ
32
Introduction
This action involves issuance of a permit to demolish the Jackling
House, an architectural gem and seminal historical resource of local, state,
and national import. Designed by
renowned architect George Washington Smith and built for copper magnate Daniel
C. Jackling in the Spanish Colonial Revival style, the Jackling House has many
remarkable fixtures of copper and copper alloy, reflecting JacklingÕs
leadership in the copper industry.
Real Party in Interest Steven P. Jobs seeks demolition of this historic
single-family house in order to build a different house on a twelve acre site
in the Town of Woodside.
The case turns upon the substantive mandate of the California
Environmental Quality Act (ÒCEQAÓ): to protect the environment, including the
historic ÒbuiltÓ environment, each lead agency Òshall mitigate or avoid the significant effects on the
environment of projects that it carries out or approves whenever it is feasible
to do so.Ó (Pub. Resources Code ¤21002.1, italics added; see also ¤ 21002.)
Thus, no public agency shall approve a project for which an
environmental impact report (ÒEIRÓ) has been certified which identifies one or
more significant environmental effects Ñ including impacts to historic
resources Ñ unless specific economic, legal, social, technological, or other
considerations make the mitigation measures or alternatives identified in the
EIR infeasible. (Pub. Resources
Code ¤ 21081.)
The trial courtÕs decision to issue a writ setting aside the Jackling
House demolition permit should be sustained. Appellant Woodside rejected various preservation
alternatives simply because Jobs did not want to undertake the trouble or
expense of any of them. These alternatives included both rehabilitation or
relocation of the Jackling House to another site, which would allow Jobs to go
forward with construction of his proposed house without sacrificing an
extremely significant historical building. These alternatives were determined to be feasible in the
project EIR.[1] While costly, the EIR recognized that
Jobs had the resources to undertake them and that there might also be third
parties with the resources, interest, and ability to undertake one or more
alternatives. The cost of alternatives
was not unreasonable when considered in the context of the proposed project and
the significance of the resource to be protected. If a project applicant could trump CEQAÕs mandates that
require avoidance or reduction of adverse impacts simply by declaring every
alternative or mitigation measure infeasible based upon his own personal
preferences, CEQA review would be utterly pointless.
Jobs and Woodside (collectively, ÒAppellantsÓ) argue that Jobs cannot
be forced to undertake a preservation alternative, and that therefore all
alternatives are legally infeasible.
This ignores the definition of ÒfeasibilityÓ under CEQA: Òcapable of
being accomplished in a successful manner within a reasonable period of time,
taking into account economic, environmental, social, and technological
factors.Ó (Pub. Resources Code ¤ 21061.1.) Woodside may not force Jobs to undertake a preservation
alternative, but as recognized by the San Mateo Superior Court it must deny
issuance of a demolition permit because demolition will have a significant
environmental impact and there are feasible alternatives.
Under CEQA, an agency can approve a
project with adverse impacts if there is substantial evidence that the project
would also have significant benefits, but only if it already has adopted all feasible mitigation
measures or alternatives. As
already stated, here there is not substantial evidence to support a finding of
infeasibility. Further, even if
there was evidence that all of the preservation alternatives were somehow
infeasible, there is not substantial evidence supporting WoodsideÕs strained
claim that demolishing a large historic resource will benefit a vague and
unspecified General Plan goal of open space preservation.
Thus, Woodside abused its discretion both
by approving demolition without substantial evidence that all alternatives and
mitigation measures were infeasible, and by adopting an unsupported statement of overriding
considerations. The Judgment
should be affirmed.
Statement
of Facts
I. THE
HISTORICAL SIGNIFICANCE OF THE JACKLING HOUSE.
The Jackling House, with its many striking copper and copper alloy fixtures, is historically significant and is eligible for listing on the California Register of Historical Resources because of its association with Daniel C. Jackling, a dominant figure in the American copper industry, and because the construction of the House reflects JacklingÕs role in the copper industry. (Administrative Record Volume 2, page 533-534, hereinafter cited Ò_:_Ó) The Jackling House is an impressive example of Spanish Colonial Revival architecture, embodying the distinctive characteristics of a period (1915-1940), region (Woodside), and method of construction (double walls of wood studs and stucco), and exhibiting a high degree of craftsmanship. It is one of the most outstanding historically significant properties in Woodside. (2:534-535.) The Jackling House is located on twelve acres of land owned by Jobs in Woodside (3:817) and is visible from the road and nearby open space areas. (2:501.)
The
House was designed by George Washington Smith, the leading Spanish Colonial
Revival architect of his day.
(2:734.) He is considered
to be Òone of the most important architects of California houses in the first
half of the 20th century.Ó
(2:733.) Because Smith was
such a notable California architect, his designs and drawings, including those
for the Jackling House, are kept in the University of California Santa
BarbaraÕs Architectural Design Collection. (3:1096.) Smith designed homes and buildings throughout California
communities, including Santa Barbara, Pebble Beach, San Francisco, and
Woodside. (2:735; 3:1097; 3:1099.) Two George Washington Smith homes were built in Woodside:
the Jackling House and the Dr. Herbert Moffet residence; both appear in the
book George Washington Smith, An ArchitectÕs Scrapbook.
(3:1097.)
II. OWNERSHIP AND
USAGE OF THE JACKLING HOUSE.
The Jackling House was designed in 1925 and finished in 1926. (2:731.) It remained the JacklingsÕ home until 1957. (2:732.) After 1957, it had various other owners until, in November
1984, Jobs acquired it. (1:77,
2:732, 816.) He used the House as
his primary residence for approximately ten years. (3:817, 820.) Thereafter he
moved to Palo Alto and rented the House to friends for several years. (3:817,
820.) Then, starting around 2000,
Jobs stopped having anyone live in the House, and allowed it to deteriorate.
(3:817, 820.) Since then, there
has been vandalism and some destructive asbestos removal. (3:817.) Jobs later purchased the three-acre
property next door. He wants to
tear down the Jackling House and the residence on the adjoining lot in order to
build one new single-family residence on the total 12 acres. (3:818.)
III. DEMOLITION PERMIT
APPLICATION AND REVIEW.
Jobs has yet to submit an application for a building permit for a new
house, and there is no estimate of its anticipated cost, and no information
about its likely nature or style.
(2:452.) The only details regarding
the proposed new house in the Administrative Record is that Jobs agreed to
limit the new residence to approximately 6000 square feet if the demolition
permit were granted, which is the maximum allowed by Woodside planning and
zoning requirements.
(2:452-453.) However, the
project for the purposes of this case is the demolition of the Jackling House and the construction of a new house. (2:450-451.)
A
Draft EIR, released for public review on January 27, 2004 (2:494) analyzed the
impact of demolition of the Jackling House. In it, an architectural historianÕs historic resources report
documented the reasons why the Jackling House meets two of the four criteria
for listing on the California Register of Historical Resources, any one of
which is sufficient for listing, as it is both Òassociated with the lives of
persons important to local, California, or national historyÓ and Òembodies the
distinctive characteristics of a type, region, or method of construction, or
represents the work of a master, or possesses high artistic values.Ó
(2:708-740.) Other historic
architecture experts fully concurred with the EIRÕs conclusion that the
Jackling House was eligible for listing on the California Register of
Historical Resources. (2:741.)
The
Final EIR was released on May 20, 2004.
It analyzed five preservation alternatives: (1) no project (2:550); (2) renovation (2:551); (3)
renovation plus addition (2:557); (4) relocating the House onsite (2:564); and
(5) relocating it offsite (2:570).
As stated in AppellantsÕ opening brief, Jobs Òcould not have been more
emphaticÓ in his rejection of all of these alternatives, and insisted he should
be granted a demolition permit. (AppellantsÕ
Opening Brief (ÒAOBÓ), p. 18.)
In
a letter dated May 27, 2004 to the Woodside Planning Commission, Susan
Brandt-Hawley, a prominent California historical preservation attorney who
served as WoodsideÕs special legal counsel in this matter, wrote:
The Town has no obligation to approve the requested demolition of an historic resource. The Town cannot require rehabilitation of the Jackling House, but it may choose to deny its demolition since it will have a significant environmental impact. The fact that the valuable residence remains on the property and that according to the EIR its rehabilitation is feasible reinforces the fact that the applicantÕs objective of a single-family residence may be achieved without demolition. The applicant is left with viable, beneficial, non-demolition uses of his historic property.
(3:1075-1076.) Although JobsÕ attorney argued in a June 8, 2004 letter to the Planning Commission that denial of the demolition permit for the project Òwill not preserve the Jackling HouseÓ and that Jobs Òcannot legally be required to maintain the structureÓ (3:1239), Brandt-Hawley also had noted,
The current deteriorated condition of the Jackling
House is due to the ownerÕs lack of maintenance as well as his deliberate
actions taken to leave the house open to the elements and birds. . . . In my
opinion, any reprise of destructive activities should be construed as
demolition by neglect; a conscious action taken by Mr. Jobs to achieve
demolition without a permit. If
the Town does not grant a demolition permit, under its police powers it may
prohibit any reprise of demolition by neglect.
(3:1232-1233.)
In a June 2, 2004 report, the Planning Commission staff recommended
that the Planning Commission deny the
demolition permit and find that the significant environmental impact of
demolition was not outweighed by overriding public benefits. (2:782-788.) It
noted that the demolition would be contrary to the architectural and site review provisions in
WoodsideÕs Municipal Code Section 153.221, which Òencourage[s] the maintenance,
rehabilitation, and improvements of existing buildings and structures.Ó
(2:783.)
The trial court described the subsequent
factual history[2]:
Instead,
at its meeting of June 2, 2004, the Woodside Planning Commission approved the
demolition permit. . . . Jobs indicated that he did not like the look of the
existing house and that it was rundown. AR 816. He also admitted that he
allowed the house to fall into disrepair because he wanted to tear it down
anyway. JobsÕ attorney argued that all of the alternatives were not
economically feasible. He also indicated that Jobs did not have any designs or plans for the anticipated new
residence - Jobs Òdid not wish to design the new residence until receiving
permission to demolish the old estate.Ó AR 795. . . . The
Planning Commission was informed that if any of the alternatives were deemed
ÒfeasibleÓ then the demolition must be denied and the proposed project
disapproved. AR 839.
(Joint Appendix (hereinafter ÒJAÓ)
129-130.) The staff report for the
June 16, 2005 Planning Commission hearing stated that there was no evidence of
infeasibility or of an overriding benefit. (3:888.)
During WoodsideÕs administrative review of
the demolition permit application, demolition of the Jackling House was opposed
by the Woodside History Committee (3:1100), the National Trust for Historic
Preservation (3:1112-1114), and
local residents, including members of RespondentÕs group. (3:1038-1044; 3:1093-1095;
3:1107.) The State Historical
Resources Commission also opposed the demolition. The Commission is the agency established under State law to
protect CaliforniaÕs historical resources. (Pub. Resources Code ¤¤ 5020.4 (a)(8) and 5024.1 (a); Title
14, Cal. Code Regs. (ÒCEQA GuidelinesÓ), ¤ 15064.5 (a)(1).) The agency stated, ÒThe loss of the
Daniel C. Jackling residence . . . , either through demolition or
inappropriate relocation, would be a loss to the cultural heritage or [sic] the
State of California and the nation.Ó
(3:1098.)
As
the trial court stated, despite all of the opposition to demolition:
The
Planning Commission adopted and certified the final EIR, but ordered the staff
to draft new findings, i.e., findings that there was an overriding benefit
supporting demolition of the historic building. AR 798. Yet, the Planning Commission was unable to
articulate the basis of its decision. On the contrary, it voted to Òcontinue
the discussion to meeting of June 16 to allow the Commissioners to consider the
reasons why each alternative is infeasible and articulate why the statement of
overriding consideration should be prepared to allow the approval of the
demolition permit. AR 798.
At
the next meeting on June 16, 2004, counsel for Jobs proposed to the Planning
Commission that they make findings of overriding considerations based upon the
Town's General Plan. AR 893-901. The basic thrust of the finding is that
tearing down the Jackling House would allow the building of a smaller residence
in conformity with existing Town specifications and zoning. Several
commissioners believed that Òopen spaceÓ was an overriding consideration. See
AR 920, 921, 925, 931. The
Planning Commission approved the Statement of Overriding Consideration and
approved the demolition permit. AR 906.
As
part of its findings, the Planning Commission found that all five project
alternatives Òare not feasible.Ó AR 956. Specifically, Alternative #1 (no project) Òfails to meet the project objectives and
does not protect an historic resourceÓ; and that Alternatives #2, #3, #4 and #5
are Òeconomically unjustifiableÓ. After finding that no alternatives were
viable, the Planning Commission held that allowing the demolition with certain
conditions added (of a mitigating nature) would be consistent with the General
Plan, particularly as to open space. AR 958-960.
(JA 130-132.)
Three individuals appealed the Planning CommissionÕs
approval of the demolition permit to the Town Council. (3:1195-1197.) In a September 15, 2004 letter to the
Town Council, then California State Historical Resources Commission Chair Dr.
Anthea Hartig concurred with the EIRÕs finding of historic significance. (3:1098.) She stated that loss of the Jackling House would be a loss
to the cultural heritage of the State of California and the nation, and that
the House is a Òwork of great
significance.Ó (3:1099.)
The
Woodside Town Council considered the appeals on December 14, 2004. WoodsideÕs staff again recommended
denial of the demolition permit, reaffirming that the Jackling House meets the
criteria for listing as a state historical resource. (3:1173.) In
the report, Woodside Director of Planning and Building Hope Sullivan explained:
Staff does not find that the project as proposed
offers any benefits that would allow the Town Council to adopt a Statement of
Overriding Consideration. Further,
since there are feasible alternatives to demolition, a Statement of Overriding
Considerations is not allowed by CEQA (Public Resources Code section
21081.) A Statement of Overriding
Considerations may be considered only if there are not feasible alternatives to
demolition and the significant environmental impact of the loss of an historic
resource is therefore unavoidable.
That is not the case here.
(3:1175; emphasis added.) Staff recommended a finding that ÒThere is no substantial
evidence in the record that alternatives identified in the EIR are infeasible.Ó
(3:1186.)
At the December 14, 2004 hearing of the Town Council, Sullivan emphasized
CEQA does recognize that specific . . . benefits of a proposal may outweigh the unavoidable environmental effects, making the environmental effects acceptable. This can only be done if the project alternatives are not feasible, and I do believe they are feasible.
(4:1280, emphasis added.) She pointed to relocation as a feasible alternative, noting Òthe level of interestÓ expressed by individuals in relocating the House. (4:1301.) Ms. Sullivan referred to Appendix 7 of the EIR and stated relocation was estimated to cost roughly $700,000 to $800,000. (4:1303.) Following press coverage of the Planning Commission decision, scores of individuals had inquired about restoring the House. (3:1119-1123.) The inquiries were a spontaneous response to the press coverage rather than a response to any affirmative effort by Woodside or Jobs to find someone interested in relocating the House. (4:1313-14.)
On December 14, 2004, WoodsideÕs Special Counsel commented on the Planning CommissionÕs finding that benefits of the project outweighed its impacts. She stated:
[T]he argument is made that because Mr. Jobs does not want to . . . rehabilitate the house, that in fact that is an infeasible alternative, because thatÕs not something that the applicant wishes to do.
And I would just like to point out that that is not a grounds for infeasibility, and in fact if you think about CEQA, the point of the environmental law is to look at project alternatives to avoid environmental impacts. If an applicantÕs refusal to accept an alternative was a grounds for infeasibility, then it guts the statute. If any developer wants to build a project he wants to build, his refusal to do anything else is not a grounds for infeasibility.
(4:1283.)
WoodsideÕs Special Counsel noted that she had brought and submitted to
the Woodside Planning Department a recent Superior Court decision from Santa
Clara County that lengthily discussed and dismissed a similar argument that a
developerÕs unwillingness to consider an alternative made it infeasible.[3] She further reminded the Town Council
that it could not even consider the overriding benefit to Woodside if there was
a feasible alternative, and that Staff and the EIR had concluded there were
feasible alternatives.
(4:1297.)
Contrary to staffÕs and counselÕs
recommendations, the Town Council
voted 4-3 to adopt a statement of overriding considerations and approved the
demolition. (4:1391-1392.)
Woodside
did condition its approval of the demolition by providing that the permit would
not be issued for twelve months,
during which time Jobs Òshall work with the Town to market the main house. . .Ó
for relocation, with Jobs to donate
a reasonable amount, as determined by the Town Manager, to the cost of the moving of the main house to a new location.
(4:1397.)
I. Woodside Violated CEQA by Approving Demolition
of a Significant Historical Structure Without SuBSTANTIAL Evidence of
Infeasibility of Alternatives.
A. CEQAÕs
Substantive Mandates Encompass Historical Resources and Denial of a Project is
Required When There Is a Feasible Alternative.
1.
CEQA
Contains Substantive Mandates.
The Òpolicy of the stateÓ reflected in CEQA is that projects with significant environmental impacts may not be approved Òif there are feasible alternatives or feasible mitigation measures available which would substantially lessen the significant environmental effects . . .Ó (Pub. Resources Code ¤ 21002.) More specifically, CEQA states:
Pursuant to the policy stated in Sections 21002 and 21002.1, no public agency shall approve or carry out a project for which an environmental impact report has been certified which identifies one or more significant effects on the environment that would occur if the project is approved or carried out unless . . .:
(a). . . (3) Specific economic, legal, social, technological, or other considerations . . . make infeasible the mitigation measures or alternatives identified in the environmental impact report.
(Pub. Resources Code ¤ 21081.)
Appellants wrongly state ÒAside from the requirement to prepare an EIR- a purely information as opposed to regulatory document-- no affirmative obligation flows from CEQA. . .Ó (AOB, p. 28.) Contrary to AppellantsÕ denial of an affirmative obligation imposed by CEQA, it is settled law that:
CEQA
contains substantive provisions
with which agencies must comply. The most important ... is the provision
requiring agencies to deny approval of a project with significant adverse
effects when feasible alternatives or feasible mitigation measures can
substantially lessen such effects.
(Sierra Club v. Gilroy City Council (1990) 222 Cal.App.3d 30, 41, italics added.) Indeed, in a case decided on July 7, 2006, a court analyzed the Òsubstantive mandateÓ of CEQA, then set aside a college campus master plan project because there was not substantial evidence to support a college districtÕs findings of economic and legal infeasibility of mitigation. (County of San Diego v. Grossmont-Cuyamaca Community College (2006) ÐCal. App.--, slip opinion, pp. 18-29[4].)
ÒFeasibleÓ is defined as Òcapable of being accomplished in a successful manner within a reasonable period of time, taking into account economic, environmental, social, and technological factors.Ó (Pub. Resources Code ¤ 21061.1.) The definition does not require the agreement of the project applicant. ÒEach public agency shall mitigate or avoid the significant effects on the environment of projects that it carries out or approves whenever it is feasible to do so.Ó (Lincoln Place Tenants Ass'n v. City of Los Angeles (2005) 130 Cal.App.4th 1491, 1508, emphasis added.)
2. CEQAÕs
Substantive Protections Include Historic Resources.
Since its inception, CEQAÕs substantive protections have encompassed
historic resources. The Supreme
Court reiterated in Friends of Sierra Madre v. City of Sierra Madre (2001) 25 Cal.4th 165 that while CEQA is Òdirected
primarily to ecological concerns and preservation of the environment,Ó it is
Òthe policy of the state to Ôpreserve . . . examples of the major periods of
California history.ÕÓ (Id. at
183-184; Pub. Resources Code ¤ 21001 subd.(c).) Indeed, the Legislature has committed to Òtake all action
necessary to provide the people of this state with . . . historic environmental
qualities.Ó (Pub. Resources Code ¤
21001, subd.(b).) Thus, ÒA project
that may cause a substantial adverse change in the significance of an
historical resource is a project that may have a significant effect on the
environment.Ó (Pub. Resources Code
¤ 21084.1.) Demolition of
the Jackling House, a significant historical resource, thus would cause a
significant adverse effect on the environment within the meaning of Public
Resources Code section 21084.1.
(4:1396.)
Despite WoodsideÕs agreement regarding the significance of the Jackling
House, the Town Council erroneously agreed with Jobs that the expense of the
alternatives made them infeasible.
Appellants claim that ÒfeasibleÓ does not include a thing that is
Òunlawful or economically unrealistic,Ó and that the alternatives Òwere all
both financially and legally infeasible.Ó
(AOB, p. 16, emphasis original.)
As discussed below, substantial evidence in the record does not
establish that alternatives identified in the EIR are either economically or
legally infeasible.
B. Evidence About the Cost of the Demolition and Construction Project Does Not Support the Finding of Infeasibility of All Alternatives.
The bare cost of an alternative is insufficient to show it is financially infeasible:
The fact that an alternative may be more expensive or less profitable is not sufficient to show that the alternative is financially infeasible. What is required is evidence that the additional costs or lost profitability are sufficiently severe as to render it impractical to proceed with the project.
(Citizens of Goleta Valley v. Board of Supervisors (Goleta I) (1988) 197 Cal.App.3d 1167, 1181, emphasis added.)
Appellants claim that WoodsideÕs determination that alternatives were infeasible was based on substantial evidence consisting of cost estimates ranging from approximately $4.9 million to $9 million (AOB, p. 20 and 22), although the costs of relocating the Jackling House to another site was estimated to be $700,000 to $800,000. (4:1303.) Simply stated, Woodside failed to obtain the evidence that would allow it to evaluate the economic feasibility of these alternatives. There was little reference to the monetary resources available to Jobs, although his billionaire status is a matter of common knowledge; there was little evidence regarding the value of the property, either with or without the Jackling House; and there was no evidence about the cost of the proposed demolition and construction project. Additionally, JobsÕ attorney himself stated that Òwe have uncovered a tremendous amount of interest in people who want to move and restore the house.Ó (4:1314.) As discussed below, evidence in the record showed that relocation was economically feasible, and there was no evidence that other alternatives were infeasible.
1. The
Amount of Money Required for Preservation Alternatives, Without Context, is
Insufficient to Show Infeasibility.
Appellants wrongly state that Ò[t]he very size of the amounts required
[for preservation] constitutes substantial evidence to support a finding of
economic infeasibility, without more.Ó
(AOB, p. 21.) This
assertion is directly contradicted by settled law: increased costs or reduced
profits alone do not equate to
infeasibility, since such costs must be Òsufficiently severeÓ to render it
Òimpractical to proceedÓ with a project.
(Goleta I, supra 197 Cal.App.3d 1167, 1181.) In this case, there was no evidence to show additional costs
were so severe that it would be impractical to proceed with the project. On the contrary, the limited evidence
in the record tends to show that in the context of this project, the
alternatives are economically and
legally feasible.
Alternatives are not infeasible merely
because they appear to be expensive.
Any meaningful statement about infeasibility requires a context within
which to gauge it. As discussed
below, the context disclosed in the cases upon which Appellants rely (AOB, pp.
20-23) for findings of economic infeasibility either focus on the overall cost
and profitability of the proposed projects (Maintain Our Desert Environment
v. Town of Apple Valley (ÒMODEÓ) (2004) 124 Cal.App.4th 430; San Franciscans
Upholding the Downtown Plan v. City and County of San Francisco (2002) 102 Cal.App.4th 656), or upon
evidence about the extent of the resources available to the project applicant (City
of Fremont v. San Francisco Bay Area Transit District (1995) 34 Cal.App.4th 1780, 1787). Such evidence is absent in this case.
a. Information
About the Full Scope of the Project Was Required to Provide Context.
Appellants unfairly criticize the trial courtÕs analysis because it
Òdepended upon a definition of the ÔprojectÕ as not just a demolition, but
demolition plus construction of a new residence.Ó (AOB, p. 14.)
The trial court in fact correctly analyzed the whole of the
project. Respondents in Lincoln
Place, supra, 130 Cal.App.4th 1491,
tried to draw a legally erroneous narrow project description as Appellants
similarly attempt to draw in this case. This narrow definition was rejected by
the Court:
We find the distinction drawn by the city and the
owners between the Ôdemolition projectÕ and the Ôredevelopment project,Õ is
disingenuous at best. Under CEQA a ÔprojectÕ is
Ôan activity which may cause either a direct physical change in the
environment, or a reasonably foreseeable indirect physical change in the
environment[.]Õ This definition is
amplified in the Guidelines which define a ÔprojectÕ as Ôthe whole of an
action, which has a potential for
resulting inÕ a direct or indirect physical change in the environment.
(Lincoln Place Tenants Ass'n v. City of Los
Angeles, supra, 130 Cal.App.4th at
1507 [citations omitted].) Despite
the settled law in this regard, Appellants claim that Òit is the demolition and
the demolition alone that defines the project for purposes of CEQA.Ó (AOB, p. 15.) For purposes of analyzing the feasibility of alternatives
and mitigation measures in the EIR, the ÒprojectÓ must encompass the Òwhole of
an action,Ó not each individual associated approval. (Lincoln Place Tenants, supra, 130 Cal.App.4th at 1507.) Appellants imply that the trial courtÕs
reasoning about the extent of the project somehow challenged the project
description in the EIR. (AOB, p.
14.) However, the project
description in the Final EIR was valid as it stated that the project included
clearance of the site Òto prepare the site for eventual construction of a
single-family residence.Ó (2:501;
accord 2:507-8.) A councilmember
verified, ÒNow itÕs been submitted as a demolition and building of some
undefined house.Ó (3:832, emphasis added.) Appellants acknowledged the project
goal was preparing for construction of a new residence, not just demolition of
the Jackling House.
b. Consideration
of Context is Required Because the Costs of Mitigation Vary With a ProjectÕs
Impacts.
For larger, more expensive, or environmentally damaging projects,
significant expenditures for mitigation measures may be appropriate. In one case, mitigation measures worth
$674 million were part of a project approval for a ÒResidential Neighborhood
Protection ProgramÓ and other mitigation measures
under an urban development plan for a 1.5 square mile area. (Los Angeles Unified School Dist. v.
City of Los Angeles (1997) 58
Cal.App.4th 1019, 1030.) In
another case, $10 million in mitigation was provided to counter the groundwater-contaminating
effects of a proposed landfill on third parties. (Cadiz Land Co., Inc. v. Rail Cycle, L.P. (2000) 83 Cal.App.4th 74, 96.) The expense of these measures was
appropriate in the context of the projects proposed. With no context, there is no way to judge the reasonableness
of the expenditures required for mitigation of a projectÕs impacts.
Although the appraised fair market value of the property is not found
in the Administrative Record, the Record reflects that a buyer in Woodside
recently purchased 11 acres that was part of the former Jackling Estate for
Òthe astonishing price of $52.5 million.Ó
(1:283.) Jobs wishes to
build his new home on 12 acres.
(3:817.) While the rehabilitation would be costly, is certainly
possible that Jobs may seek a permit to build a house that costs more than
rehabilitating the Jackling House - a house he previously lived in for 10
years. Although little information
is contained in the Record, what is known shows the context of the project is a
unique historical resource that is considered highly valuable by many people
and the location is the community of Woodside, where real estate prices are
very high. Appellants claim ÒinferencesÓ or Òcommon knowledgeÓ of
council members support the conclusion of infeasibility. (AOB, p. 23.) However, as discussed further below, those ÒinferencesÓ or
Òcommon knowledgeÓ are not stated in the record, thus violating the principle
that a public agency must explain its analytic route. (Village Laguna of Laguna Beach v. Board of Supervisors
of Orange County (1982) 134
Cal.App.3d 1022, 1034-1035.)
c. AppellantsÕ
Cases are Inopposite because those Cases Included an Economic Analysis.
One possible method of evaluating economic feasibility of an alternative is a comparison of the overall cost of the project to the market value of a project site or the value of the project. During administrative review before Woodside, a member of the public identified the lack of a Òcomparison of costs of demolition and constructing a new residence versus the cost of rehabilitating the Jackling House as a residenceÓ as one type of evidence that was lacking to support the TownÕs decision that renovation was economically infeasible. (3:995.)
There is no evidence of any economic analysis whatsoever to compare the
cost of the proposed alternatives (which costs are estimated in the EIR, except
for the relocation alternative) versus the cost of the proposed project,
including the estimated cost of the new residence. The ÒpurposeÓ of
the project is to tear down a single family residence in order to build a
single family residence. (2:497,
507 [project objective is clearance of site Òto prepare the site for the
eventual construction of a single-family residenceÓ], 508.) No
costs of building the new residence were provided to the Town Council because
Jobs declined to provide any designs, plans, or specification of the new
residence until after his demolition permit is granted. (2:522 [Òspecific details of that
residence have not been submitted to the TownÓ].) Thus, there is no cost comparison or analysis supporting any
of these findings that each of the alternatives are Òeconomically
unjustifiable.Ó
Appellants contend that in San
Franciscans Upholding the Downtown Plan. v. City and County of San Francisco (2002) 102 Cal.App.4th 656, this Court
held that reports describing Òthe huge costs of each historic preservation
alternative were sufficient to support findings that the alternatives were
infeasible.Ó (AOB, p. 21.) San
Franciscans involved a redevelopment
project at the site of the former Emporium store in downtown San
Francisco. Detailed financial
reports prepared by independent real estate valuation experts provided
information about the revenue streams that could be expected to be generated
from each of the alternatives. (Id. at 693 [Ò[A] report calculated the development costs
and projected revenue stream for the preferred Project and each preservation
alternative in order to determine the return an investor could expect to make
and the consequent amount a prudent person might invest given the expected
revenue stream. . . . The financial gap . . . represented a shortfall that would have to be made up with
public investment.Ó]) The
independent economic analysis revealed that the most preservation-oriented
alternative would require $82.1 million in public investment to Òclose the
financial shortfall between private investment and cost of rehabilitation and
development.Ó (Id. at 694.)
The type of independently-verified economic analysis comparing initial
investment cost to potential revenue streams available in San Franciscans is not available here.
Appellants imply that City of Fremont
v. San Francisco Bay Area Transit District (1995) 34 Cal.App.4th 1780 upheld a finding of financial
infeasibility Òbased solely on the cost of an alternative.Ó (AOB, p. 23.) That implication is wrong because the record in that case
contained substantially more evidence than merely the cost of an alternative.
In City of Fremont, the California
Legislature had passed a bill that required Bay Area Rapid Transit (ÒBARTÓ) to
begin constructing a line extension to service the Warm Springs area by
December 31, 1991, if certain conditions were satisfied. (Id. at 1784.)
Because of this mandate and
time limit, BARTÕs budget and the availability of funding represented
particularly rigid limiting factors.
BART proposed constructing an aerial rapid transit route extension. (Id., at pp. 1783-1785.) Among the project alternatives, the EIR considered
constructing the extension underground; however, it concluded that this alternative would cost $60 million
more than the project, and therefore was economically infeasible. (Id., at pp. 1785, 1787.) In affirming BARTÕs action, the Court did not rely upon the
sheer size of the $60 million number.
The record in City of Fremont contained
evidence of limitations on BARTÕs funding resources:
However, the cost of the subway alignment in Central
Park is in excess of BART's current funding resources, and is, as a consequence, currently infeasible for
economic reasons.
(Id. at
1787, italics added.) There was
discussion of the limits of BARTÕs funding capabilities:
The tables discussed above, clearly reflect BART's
estimate that a subway would cost up to $60 million more than an aerial
structure, an amount in excess of BART's funding capabilities.
(Id. at
1788.) Thus, there was evidence
BARTÕs Òfunding resourcesÓ and Òfunding capabilitiesÓ were exceeded that
supported a decision to find alternatives infeasible. The careful cost estimates and analysis lead to an
inescapable conclusion because they were within a meaningful frame of
reference: solid evidence that one alternative would cost $60 million more than
the selected project, plus the fact that BART could not pay that extra $60
million, indicated that the alternative was economically infeasible. City
of Fremont was not a situation where
costs in isolation were used to support a finding of economic infeasibility, or
where a big number, by itself, determined infeasibility. Unlike City of Fremont, here there is no evidence of any limitations on
JobsÕ funding resources or capabilities. Additionally, in contrast with the City
of FremontÕs time limitation to
construct a subway, Jobs has indicated that he is under no time
constraint. (3:819. [ÒIÕm just in
this for the long haul and IÕm not living there, so IÕve got time . . .Ó].)
Terms
such as Òinfeasible,Ó Òimpractical,Ó or Òeconomically
unjustifiableÓ can be entirely subjective and arbitrarily applied if they are not
provided in a context and with a frame of reference to allow comparison with
what is feasible, practical, or
economically justifiable. Foundation for San FranciscoÕs
Architectural Heritage v. City and County of San Francisco (1980) 106 Cal.App.3d 893, cited by Appellants (AOB,
21, 30), provides insight into the type of data that could have
been supplied in the record, but was not, in this case. Foundation involved demolition of the historic City of Paris
building and construction of a new building by Neiman-Marcus in San
Francisco. (Id. at 898.) The
base construction cost for the project was known and Òeach of the alternatives
considered would have increased construction costs from 1.5 million dollars to
over 4 million dollars.Ó (Id. at 913.)
Evidence in the record supported findings that
The developer cannot use the City of Paris Building in its present configuration or in any rehabilitated or renovated configuration as a retail specialty store. . .
There is no evidence that another developer exists who is willing to acquire and rehabilitate the existing structure and who has the financial and technical ability to do so. ...
(Id. at 904.)
In the present case, the cost of the whole completed project is an unknown quantity. In contrast with the facts in Foundation, evidence in the record shows that Jobs could use the House as a residence and has done so in the past. As discussed below, there is also evidence that other individuals exist who have the willingness, financial ability, and technical ability to acquire the Jackling House, relocate it, and restore it.
In contrast with Foundation, San Franciscans, and City of Fremont, in this case there are no economic analyses or cost
comparisons to substantiate AppellantsÕ assertions of infeasibility of
alternatives. Without such
comparative evidence, Woodside had no basis for concluding alternatives were
economically infeasible.
2. Evidence about the Financial Resources of the Project Applicant Conflicts with the Finding of Infeasibility.
One factor to consider in determining economic infeasibility could be the resources available to the project applicant. Appellants claim ÒTown Staff was divided regarding the relevance of JobsÕ financial positionÓ (AOB, p. 20, fn. 28) but WoodsideÕs special legal counsel believed that JobsÕ financial position was relevant. WoodsideÕs Special Counsel stated that to evaluate economic feasibility, Woodside would need to Òlook at costsÓ and Òlook at capability.Ó (4:1299). She also stated,
the means of the applicant [is] one way to consider [financial feasibility] . . . whatever judgment you make about the feasibility of an alternative . . . must be based on evidence of some kind. So we canÕt just say ÔOh, this alternative looks really costly. . . [T]he means of the applicant is one way to consider [financial feasibility], but youÕre certainly not limited to that.
(3:840.)
The evidence in the record indicates that
Jobs has the means to pay for any of the various alternatives, including the
alternative of mitigating the loss of the Jackling House by moving it
off-site. A statement by the Mayor
of Woodside indicates that Jobs, the chief executive of Apple and Pixar (3:966)
Òhas the meansÓ to pay for mitigation, although the mayor viewed mitigation
costs as unreasonable.
(4:1383.)
Appellants claim that the decision in MODE, supra, 124 Cal.App.4th 430, establishes that the
financial situation of a project applicant is never relevant to determining
economic infeasibility. (AOB, p.
20.) This is incorrect. In MODE, the Court evaluated the evidence about the economics
of a commercial retail center.
Since it was a commercial activity that presumably would not be
undertaken were it not profitable (initial investment recovered and exceeded by
expected future income from the project), the Court stated:
The fact that a project costs too much to be
profitable or cannot operate at a profit so as to render it impractical does
not hinge on the wealth of its proponent.
No proponent, whether wealthy or not, is likely to proceed with a
project that will not be economically successful. But, if the project can be
economically successful with mitigation, then CEQA requires that mitigation,
regardless of the proponent's financial status. (Ibid.)
(MODE, supra, 124 Cal.App.4th at 449, emphasis added.) For a commercial venture such as the proposed distribution
center in MODE, where a profitable
return on an investment is required, the wealth of an applicant may be
irrelevant since an unprofitable venture would not be undertaken by any
applicant. The Court stated that a
finding of the impracticality of a commercial project Òdoes not hinge on wealth
of [the project] proponentÓ but this does not foreclose the possibility that it
may be relevant in other contexts.
Since the profit motive is not implicated in JobsÕ decision about his
personal residence, a single family residence could be built in an
Òeconomically successfulÓ way with relocation as mitigation. MODE thus supports RespondentÕs position: Òif the project can be economically successful
with mitigation, then CEQA requires
that mitigation.Ó (Ibid., emphasis added.)
3. Evidence about Possible Outside Funding Sources Conflicts with the Finding of Infeasibility of the Relocation Alternative.
Evidence
regarding potential third-party funding that could augment the resources of the
project applicant should be considered before rejecting the economic
feasibility of alternatives. The
possibility that outside funding sources may be available is especially
important, since Appellants raise the specter of a takings claim, as discussed
below. However, in this case,
there was no independently corroborated evidence to show that the availability
of third party funding, specifically for the relocation alternative, was unlikely. Rather, uncontradicted evidence showed that it was likely
and therefore feasible.
Appellants in their brief tellingly omit
any mention that WoodsideÕs Planning Director pointed to relocation as a
feasible alternative, noting Òthe level of interestÓ that an Òundirected
marketing campaignÓ had generated in potential relocation. (4:1301.) The list of inquiries about potential relocation was
provided to Woodside by JobsÕ counsel, so Appellants cannot dispute its
veracity. (3:1302.) The list was extensive. (3:1119-1123.) It likely included people whose
business is to acquire historic properties, relocate and refurbish them, then
sell them at a profit, since there is a market for historic homes. One inquiry came from a person who Òhad
done restoration of [George Washington] Smith homesÓ and was ÒCurrently moving
2 residences off property owned by Ty Warner (of Beanie Baby fame).Ó (3:1121.) Two other callers were noted
as Ònot put offÓ or Ònot shockedÓ at the estimate to move the House. (3:1122.) The summary of the list stated ten callers were ÒProbably
serious and possibly able to actually relocate and reassemble.Ó (3:1123.) Counsel for Jobs tellingly informed the Town Council that
although some callers were Òtire kickersÓ, on the other hand, Òsome of them [people
expressing interest in relocation] IÕve talked to and I think they are serious
and could capably do the [relocation] job.Ó (4:1315.)
Therefore, the evidence that relocation was a feasible alternative was
supplied by JobsÕ counsel and was uncontradicted by any facts in the record.
Based upon the level of interest in
relocation, WoodsideÕs Planning Director stated:
And maybe if in the intervening time [between the Planning Commission decision and Town Council meeting] I hadnÕt seen the level of interest and you have the list of the phone calls and the people who have contacted them, the 60 people, if we hadnÕt seen that level of interest, I might be mulling it [relocation] over a little more. But I just feel like itÕs something that truly is feasible.
(3:1302.)
Woodside imposed as a condition of
approval of the demolition permit that the House be held open for sale and
relocation for one year. (3:906
[requiring effort to Òmarket the estateÓ]; 4:1397.) Appellants admit that the conditions imposed upon approval
of demolition, including requiring that the House be Òmade availableÓ for
potential relocation, Òhad the potential to restore the Residence in a new
location.Ó (AOB, p. 35.) Thus, by
their own admission, relocation (whether funded by Jobs, a third party, or a
combination of the two) was a
feasible option. Yet the
relocation of the House was not made a mandatory mitigation measure, but just
an open possibility for one year.
Woodside staff pointed out that Ò[t]he
property owner owns an adjacent property at 95 Robles Drive. This may be a logical site for the
structure.Ó (3:1174.) Appellants contend that relocation
could cost more than the $700,000-$800,000 estimated in the EIR, depending on
the destination location (AOB, p. 20), but how much more is a matter of
complete speculation. Moreover,
other historic structures in Woodside have been successfully relocated and
rehabilitated within Woodside, which supports the conclusion that such activity
is feasible. (3:1174 [including
relocation and rehabilitation of the Mathison House Òto accommodate the TownÕs
History MuseumÓ].)
Though the imposition of the condition
requiring the House to be marketed for relocation for twelve months was a step
in the right direction, unfortunately it was not adequate to ensure compliance
with CEQA, as the ability to evaluate the feasibility of relocation proposals
was within the sole control of Jobs, not the Town Council, as it could have
been. The Town Council had no
information about what any of the interested parties may have been willing to
invest as part of a relocation project when it determined that relocation was
infeasible, since WoodsideÕs Town Council prematurely approved the project
without requiring the submission of any evidence about the content of the
responses to WoodsideÕs conditional requirement Òto market the estate.Ó (3:906;
4:1397.) As one Councilmember
correctly observed ÒthereÕs really no incentive in there to force Jobs to move
[the House]. That is if he just plays hard to get for a year, then it gets torn
[down].Ó (4:1316.) JobsÕ attorney successfully opposed
removing the time limit from the relocation condition. (Ibid.)
4. JobsÕ Opposition to Alternatives is not Substantial Evidence that they Are Infeasible.
Appellants
claim that JobsÕ Òstated unwillingness to undertake restorationÓ is itself
substantial evidence in support of an infeasibility finding. (AOB, p. 30, fn. 38.) They compound this faulty position with
the erroneous assertion that substantial evidence can be Ò. . . nothing more
than pure opinionÓ. (AOB, pp.
23-24, fn. 30, citing Pocket Protectors v. City of Sacramento (2004) 124 Cal.App.4th 903.) However, Pocket Protectors rebuts, rather than supports, AppellantsÕ claim by
confirming that Òmere argument, speculation, and unsubstantiated opinion, even
expert opinion, is not substantial evidence for a fair argument.Ó (Id. at 928-929.) Appellants
confuse apples and oranges in claiming that an applicantÕs unwillingness to
accept an alternative is substantial evidence similar to a laypersonÕs
fact-based opinion that a proposed project may have a significant environmental
impact based on aesthetics, or traffic, or some other matter within their
personal knowledge. The questions are manifestly not parallel.
Substantial evidence Òmay include facts, reasonable assumptions
predicated upon facts, and expert opinion supported by facts, but not argument,
speculation, unsubstantiated opinion, or clearly erroneous evidence." (San Franciscans, supra, 102 Cal.App.4th at p. 675, citing Pub. Resources
Code ¤¤ 21080 (e) and 21082.2 (c).)
As to the legal question of
the feasibility of project
alternatives, substantial evidence must be directed to the question of whether
or not an alternative is Òcapable of being accomplished in a successful manner
within a reasonable period of time, taking into account economic,
environmental, social, and technological factors.Ó (Pub. Resources Code ¤
21061.1.) The assertions of Jobs
and his attorney that all alternatives are infeasible, with no supporting
evidence, do not address the question at hand and are irrelevant argument and
unsubstantiated opinion. As such,
they are not substantial evidence on which Woodside could base its decision. (See Sierra Club v. County of Napa
(2004) 121 Cal.App.4th 1490, 1507,
fn. 6 [ÒWe view BeringerÕs [the proponentÕs] letter more as argument than as
evidence. . . .Ó])
Appellants claim Association of
Irritated Residents v. County of Madera (ÒAIRÓ), (2003) 107 Cal.App.4th 1383 and Foundation for San FranciscoÕs Architectural
Heritage, supra, are Òprecisely on
pointÓ in support of their assertion that opinions are evidence. (AOB, p. 30, fn. 38.) Appellants are incorrect. In both of those cases, the Òstated
unwillingnessÓ of project applicants was corroborated by objective financial
data. In AIR, supra, 107
Cal.App.4th 1383, a real party in interest presented factual evidence
to corroborate his assertion of economic infeasibility at the hearing on the
FEIR. The Court explained:
He presented an economic analysis demonstrating a negative economic return on the reduced-herd size alternative. He also presented a letter from the lending institution that was financing construction of the dairy ... The lender wrote that the reduced-herd-size alternative would not be economically feasible because it would not "generate enough cash flow to service debt on the startup operation," and that it would not finance construction of the dairy if the reduced-herd-size alternative were adopted.
(Id. at
1399-1400.) So the real party in
interest in AIR, in stark contrast
to the present case, presented an economic analysis and a letter from a lender
to corroborate his opinion that an alternative was economically infeasible.
Jobs presented no such analysis or lender letter to corroborate his opinion of
economic infeasibility. He was
simply disinclined to pursue alternatives.
A
project applicantÕs opinion about the expense of an alternative, with nothing
more, cannot constitute substantial evidence to reject its feasibility because
an applicantÕs opinion is a subjective standard, wholly within the control of
the applicant. CEQA requires
objective examination of evidence, not reliance upon a project applicantÕs
opinion of the propriety of the expense of mitigation measures or alternatives.
A project applicantÕs predilections cannot be determinative of the feasibility
of alternatives:
Since CEQA
charges the agency, not the applicant, with the task of determining whether
alternatives are feasible, the circumstances that led the applicant in the
planning stage to select the project for which approval is sought and to reject
alternatives cannot be determinative of their feasibility. The lead agency must independently participate, review, analyze and discuss the alternatives in good
faith.
(Kings County Farm Bureau v. City of Hanford (1990) 221 Cal.App.3d 692, 736,
emphasis in original.)
No applicant would prefer a project that
is more expensive, less profitable, more inconvenient, or indeed anything other
than his or her preferred design. The
applicant will understandably be biased in favor of obtaining his own project
objectives. (Foundation for San
FranciscoÕs Architectural Heritage v. City and County of San Francisco (1980) 106 Cal.App.3d 893, 907 [ÒCEQA assumes as
inevitable an institutional bias within an agency proposing a project. . .
Ò]) The applicant must provide
sufficient data, information, and reports to allow the agency to independently
perform its reviewing, analytical, and judgment functions. (Id. at 908.)
There is no authority for the proposition that an applicantÕs opposition
is the equivalent of a showing of
economic infeasibility. Appellants unreasonably seek to have this Court create
just such authority.
RespondentsÕ
reliance on authorities such as Greenbaum v. City of Los Angeles (1984) 153 Cal.App.3d 391, and No Slo Transit v.
City of Long Beach (1987) 197
Cal.App.3d 241, for the proposition that an agency is permitted to choose
between conflicting evidence (AOB, p. 24) is unavailing. In this case, there was no conflicting evidence because there was no credible evidence that all of the alternatives were
infeasible. Woodside had evidence of the cost of the alternatives, such as
relocation, but such evidence Òis not sufficient to show that the
alternative is financially infeasible.Ó (Citizens of Goleta Valley, supra, 197 Cal.App.3d at 1181, emphasis added.) In Citizens of Goleta Valley, ÒThe scant figures contained in the
administrative record [were] not sufficient to support such a conclusion.Ó (Ibid.)
In this case, there are no figures at all beyond the cost of
alternatives.
C. Conditioning the Grant of a Demolition Permit on Implementation of Preservation or Relocation Alternatives Was Not ÒLegally Infeasible.Ó
1. Woodside
Had Discretion to Deny the Demolition Project.
Appellants repeatedly claim that
alternatives requiring renovation or relocation were Òlegally infeasibleÓ
because they could not be imposed against JobsÕ will. (AOB, p. 16 [ÒTown lacked the power legally to require Jobs
affirmatively to undertake the restoration that these alternatives requiredÓ];
see also pp. 13, 18, 25, 26, 29, 31, 37.) These assertions are incorrect and mischaracterize the
nature of WoodsideÕs right to condition a demolition permit. Indeed, when one Town councilmember stated
ÒWe could deny their ability to tear [the House] down,Ó JobsÕ counsel agreed
that was ÒCorrect.Ó (4:1315-1316.)
The ability to deny or condition a
demolition permit is clear:
As long as a demolition permit process is not
conditioned on or tied to a regulation restricting the right to withdraw
residential units from the rental market, a government agency retains such
discretion to deny a demolition permit under its police power with respect to
land use.
(First Presbyterian Church of Berkeley v. City of
Berkeley (1997) 59 Cal.App.4th 1241,
1257, emphasis added.)
Appellants refer to the demolition permit
as Ònormally a ministerial actÓ (AOB, p. 15), but omit mention of WoodsideÕs
requirement for discretionary Preliminary Design Review. (2:516.) WoodsideÕs decision to grant or deny the demolition project
was discretionary, not ministerial, because it required Preliminary Design
Review by the Architectural and Site Review Board. (2:515.)
Preliminary Design Review was required under section 153.221 (D)(5) of
WoodsideÕs Municipal Code. (2:516.) AppellantsÕ citation to Prentiss v. City of South
Pasadena (1993) 15 Cal.App.4th
85, 94-95 (AOB, p. 28) highlights the importance of WoodsideÕs Code requirement
for architectural review. In Prentiss, as Appellants note, a city could not exercise
architectural control over construction of an addition to a residence because
it lacked a preservation ordinance.
Here, Woodside has an architectural review ordinance that gives Woodside
discretion to deny the permit.
Because public agencies reviewing
discretionary projects always have the power to deny the project, so long as
such denial does not run afoul of constitutional prohibitions, the agencies
have the power to approve the projects subject to conditions. (Friends of Westwood, Inc. v. City
of Los Angeles (1987) 191 Cal.App.3d
259, 273.) Appellants cite Public
Resources Code section 21004 (AOB, p. 28) to claim no affirmative obligation
Òflows independently from CEQAÓ.
What they fail to recognize is that the same section states ÒHowever, a
public agency may use discretionary powers provided by such other law for the
purpose of mitigating or avoiding a significant effect on the environment
subject to the express or implied constraints or limitations that may be provided
by law.Ó (Pub. Resources Code ¤
21004.) While Woodside may not be able to force Jobs to relocate or
rehabilitate the House, it may withhold its approval of the demolition project
unless such preservation conditions are accepted.
Appellants correctly note that in AIR, supra, 107 Cal.App.4th 1383, the County Òhad the
power to compel the applicant ... to accept a reduced maximum herd size
...Ó (AOB, p. 18, fn. 25.) The county in that case had exactly the
same power to ÒcompelÓ the applicant to maintain a reduced herd size as
Woodside has in this case to ÒcompelÓ Jobs to accept a less damaging
alternative if he wishes to obtain
approval for his new house.
2.
No Statute,
Guideline, or Constitutional Provision Prohibits Imposing Conditions on Approval
of Demolition.
Appellants cite no guideline, statute, or constitutional
provision that would prevent Woodside from conditioning its discretionary
approval of the demolition and new house project. Appellants cite Sequoyah Hills Homeowners Assn. v. City
of Oakland (1994) 23 Cal.App.4th
704, 714-715 for the principle that an Òalternative is not feasible where there
is no way legally to implement it.Ó
(AOB, p. 27, fn. 34.) The
Òlegal wayÓ in which a public agency can implement mitigation measures it could
not otherwise impose is by conditioning its approval of discretionary projects on the applicantÕs
implementation of those measures (Pub. Resources Code ¤ 21004), as discussed
above. Otherwise, the project may
be denied.
In
Sequoyah Hills, there was a
specific statutory prohibition against conditioning approval of a project on a
reduction in density. Such a
condition would have violated Government Code section 65589.5, subdivision (j) that provides: ÒWhen a
proposed housing development project complies with the applicable general plan,
zoning, and development policies,Ó a local agency may not require as a
condition of approval that the project be developed at a lower density, unless
the project Òwould have a specific, adverse impact upon the public health or
safetyÓ that cannot be mitigated without lowering the density. (Gov. Code, ¤
65589.5, subd. (j)(1).) There is
no similar prohibition on denial of the demolition permit involved in this
case. In fact, Appellants have not
identified any statutory prohibition on the imposition of mitigation measures
or alternatives requiring rehabilitation or relocation in this case.
Appellants imply that there would be a
constitutional prohibition on denial or conditioning of a demolition permit
when they state Ò[a]t least one court has stated that denying a homeowner
beneficial use of his property unless she first undertakes extensive and
expensive renovation would constitute an unconstitutional taking.Ó (AOB, p. 28, fn. 36, citing State,
By Powderly v. Erickson (Minn. 1981)
301 N.W. 2d 324[5].) Denial
or conditioning of a demolition permit would not deny Jobs the beneficial use
of a house on his property, and so it could not be a taking. Jobs used the House as a residence for
approximately 10 years and his friends leased it as such for several more. (3:820.)
He could continue its residential use.
Since an economically viable use of a
property as a single family residence remains, there can be no taking. (Penn Cent. Transp. Co. v. City of
New York (1978) 438 U.S. 104,
138 [ÒNew York City's Landmarks Law has not effected a ÔtakingÕ of appellants'
propertyÓ where its restrictions Òpermit reasonable beneficial use of the
landmark site. . . .Ó]) Penn
Central is the seminal evaluation of
a takings claim in the context of preservation of a historic resource. [6] In Penn Central, the owners of Grand Central Terminal planned to build a
tower in excess of 50 stories on top of the historic terminal. After the Landmarks Preservation
Commission rejected the plans, the owners brought suit to declare the New York
Landmarks Preservation Law unconstitutional.
Among
other holdings, the United States Supreme Court held there was no
unconstitutional taking of property since there was no interference with the
ownersÕ present use of the building as a terminal, as it
had been so used for 65 years. Penn Central and its progeny demonstrate that the stateÕs objective
of preserving structures of historic significance is Òan entirely permissible
governmental goalÓ (id. at 129)
and that possible diminution of
property value caused by the historic designation that prevents demolition does
not establish a taking (id. at
131). Notwithstanding the readily
distinguishable opinions such as Benenson v. United States (1977)
548 F.2d 939, and Erickson, cited
by Appellants, Penn Central shows
that denial or conditioning of the demolition permit would not be a taking.
3. Denial
of a Demolition Permit Is Not the Same as Imposing an Affirmative Obligation to
Preserve the House.
Unable to identify a single statute,
regulation or constitutional prohibition that would prevent Woodside from
conditioning its approval of the demolition project, Appellants assert Òthe
Town lacked the legal authority to require Jobs to undertake any of the
restoration alternatives- a key fact beyond dispute.Ó (AOB, p. 13, p. 16, fn. 24, p. 25 [Town could not place an Òaffirmative obligation on Jobs to restore and
rehabilitate.Ó])
Contrary to AppellantsÕ repeated
assertions, denial or conditioning of a demolition permit is of course not the
same as affirmatively requiring Jobs to undertake restoration or
relocation. Jobs would only be
required to relocate or restore the House if he wished to rely on the permit. As discussed above, Woodside certainly
can condition its discretionary approval on relocation or restoration, so long
as those requirements do not violate constitutional protections. Indeed, under CEQA, in light of the
findings made in the EIR, it is required to do so unless the alternatives or
mitigation measures are infeasible.
Appellants
irrelevantly refer to the Òdemolition by neglectÓ discussion in a factually
distinct[7]
takings case (AOB, p. 29, fn. 29), and dispute that Jobs can be Òrequired to
maintainÓ his property by Woodside.
(AOB, p. 30.) AppellantsÕ claim
that Woodside can do nothing to remedy the rundown condition of the Jackling
House-- or for that matter, any rundown, unmaintained house in Woodside-- is
irrelevant and wrong. Ò[The
Supreme] Court has recognized, in a number of settings, that States and cities
may enact land-use restrictions or controls to enhance the quality of life by
preserving the character and desirable aesthetic features of a city. . . .Ó (Penn
Cent., supra, 438 U.S. at 129.) However, as Appellants state (AOB, p.
30), this is not an issue in this case.
II. WOODSIDEÕS Statement of Overriding Considerations is Not
supported by substantial evidence.
A. CEQA Requires Specific Findings Supported by Substantial
Evidence for the Statement of Overriding Considerations.
Even if WoodsideÕs findings that all alternatives are infeasible were
valid and were supported by substantial evidence, there is not substantial
evidence supporting the statement of overriding considerations. (4:1396.)
In
any event, subdivisions (a) and (b) of section 21081 when read together make
clear the development agency must find mitigation measures are infeasible and the benefits of the project outweigh the unmitigated
effects on the environment.
(Los Angeles Unified
School Dist. v. City of Los Angeles (1997) 58
Cal.App.4th 1019, 1030.) If significant impacts still remain
after adoption of mitigation and alternatives, the project may be approved only
with a statement of overriding considerations, which must in turn be supported
by substantial evidence in the record.
(Sierra Club v. County of Contra Costa (1992) 10 Cal.App.4th 1212, 1222.) CEQA requires
In making the findings required by paragraph (3) of subdivision (a) of Section 21081, the public agency shall base its findings on substantial evidence in the record.
(Pub. Resources Code ¤
21081.5.)
The explanation for why a statement of
overriding considerations must be supported by substantial evidence given in Village
Laguna of Laguna Beach v. Board of Supervisors of Orange County (1982) 134 Cal.App.3d 1022 is highly pertinent to the
present case, since in that case the Court held an EIR for a large housing
development project complied with CEQA, but the countyÕs findings supporting
approval based on a statement of overriding considerations were not supported
by substantial evidence. The Court
explained:
[T]he purposes of section 21081 are that there be some evidence that the alternatives or mitigation measures in the EIR actually were considered by the decision making agency and, as the Supreme Court stated in a similar situation, that there be a disclosure of Ôthe analytic route the . . . agency traveled from evidence to action.Õ [Citations.] Thus, when a project is approved that will significantly affect the environment, CEQA places the burden on the approving agency to affirmatively show that it has considered the identified means of lessening or avoiding the project's significant effects and to explain its decision allowing those adverse changes to occur. [¦]
. . . . Additionally, even though the board may have fully considered the EIR and made a wise and eminently rational decision in approving the proposed project, the board's thinking process, its Ôanalytic route,Õ has not been revealed. Only by making this disclosure can others, be they courts or constituents, intelligently analyze the logic of the board's decision.
(Id., at
pp. 1034-1035, emphasis added; accord, Resource Defense Fund v. Local Agency
Formation Com. (1987) 191 Cal.App.3d
886, 896- 898; see also Cleary v. County of Stanislaus (1981) 118 Cal.App.3d 348, 361-362; Citizens for
Quality Growth v. City of Mt. Shasta
(1988) 198 Cal.App.3d 433, 441.)
WoodsideÕs failure to explain its findings is similar to the defective statement of economic infeasibility in Village Laguna, where the Court reasoned:
Although the
Board stated that the ÒNo DevelopmentÓ alternative was economically infeasible,
it did not explain why it found the
alternative economically infeasible. Such was required by Guidelines section
15088(a) which mandates that the BoardÕs finding be Ôaccompanied by a statement
of the facts supporting each finding.Õ
(Village Laguna, supra, 134 Cal.App.3d at 1034.) At the time of the Village Laguna decision, Guidelines section 15088 provided the pertinent requirement for a statement of facts supporting each finding. Current Guideline section 15093 (b) provides a similar statement:
When the lead agency approves a project which will result in the occurrence of significant effects which are identified in the final EIR but are not avoided or substantially lessened, the agency shall state in writing the specific reasons to support its action based on the final EIR and/or other information in the record.
(Guidelines ¤ 15093 (b), italics added; see County of San Diego v. Grossmont-Cuyamaca Community College District, supra, slip opinion, pp. 16-17.)
B. WoodsideÕs General Plan Supports Preservation, Not Demolition, of Historic Resources.
Appellants contend that cases establish
that general plan policies provide ample support for findings of overriding
considerations. (AOB, p. 32.) As a general legal principle, that may
be true. However, on the facts of
this case, there is no support in the Woodside General Plan for demolition of a
historic structure in order to create open space.
The Woodside General Plan overwhelming
supports preservation of the historic Jackling House. The EIRÕs discussion of the General Plan states that the
demolition project is ÒPotentially inconsistentÓ with General Plan policy P25
which states ÒStructures of historic or architectural significance shall be
identified and documented, and efforts shall be made to preserve them.Ó (2:527.) The EIR further states
Depending on their specific design characteristics, Alternatives 2, 3, and 4 might meet the applicantÕs objectives of construction of a single family residence on the site.
(2:527.)
Thus, the only discussion of General Plan policies in the EIR finds
demolition potentially inconsistent with the General Plan, and that
alternatives to demolition might meet the applicantÕs objectives. The EIR does not discuss how the
project would purportedly implement the Open Space or other General Plan
elements, though it discusses the lack of information about future construction:
Although the applicant has indicated his intent to clear the site for purposes of construction of a single-family residence, the specific details of that residence have not been submitted to the Town.
(2:522.)
The foundation of the statement of overriding considerations adopted by
Woodside is that granting of the demolition permit is based upon Woodside's
existing General Plan: Ò[Tlhe Town Council finds that, as conditioned, the
project will provide a public benefit in implementing the Town's General PlanÓ.
(4:1393 and 1397.) The specific findings and reasons as the basis for the
Òoverriding considerationsÓ focus
on the public benefit of open space.
(4:1398.) However,
WoodsideÕs approval of demolition of an historic structure without mitigating
the significant impact of its loss is contrary to numerous specific policies of
its existing General Plan. The
General Plan does not provide a basis for approving demolition in order to
replace it with a structure of completely unknown look, style, shape, size,
color, design, layout or height.
The trial court provided a
lengthy explication that the General Plan encourages preservation and does
not provide any basis for a finding
that the approval of demolition of historic resources creates open space within
the meaning of the General Plan.
(JA, pp. 139-141.) The
General Plan does discuss open space, and it is very specific about what Òopen
spaceÓ means. It does not mean an
area of private property cleared by demolition of an existing structure. ÒOpen space uses indicated on the
General Plan Diagram are defined and described in the Open Space Element.Ó (3:1436.) These do not include the Jackling House or grounds.
The trial court correctly found that the General Plan provides that
Òopen spaceÓ has to do with areas of land that are not already improved with
structures. (JA 140-141, citing
4:1414, 1427, and 1442.) Based
upon General Community Goals G1 and G2, General Policies P11, P25, Land Use,
Community Design and Aesthetics P9, Open Space policy G6, and Housing policy
G5, the trial court noted that the major themes that emerge in the General Plan
are of conservation, preservation, and certainly maintenance of existing
structures. (JA 139-140.) Appellants completely fail to address
the overwhelming import of these policies favoring preservation, not
demolition, of historic resources.
These fundamental, mandatory policies of the General Plan cannot be
disregarded. (See Families Unafraid to Uphold Rural Etc. County v. Board
of Supervisors (1998) 62 Cal.App.4th 1332,
1342.)
Appellants do not discuss or quote a
single specific policy of the General Plan. Rather, Appellants cite a set of goals and policies that
promote preservation and conservation as Òimportant declarations of policy.Ó (AOB, p. 33, citing 4:1397-1398.) However, Appellants do not
discuss what the specific declarations actually say. One of the specific goals is ÒTo conserve open space
resources. . . .Ó (4:1398.) Such a
goal does not promote creating
open space by demolishing a structure that already exists, especially an historic
structure. Another specific goal Appellants
cite is ÒTo protect the natural beauty . . . of the natural terrain.Ó (4:1398.) Again, such a goal does not
include creating natural beauty or
natural terrain in place of an historic structure that currently exists,
especially when another structure, of unknown design, will replace a large
portion of that structure. This is
not a matter of Òreconciling superficially conflicting policiesÓ or Woodside
exercising Òbroad latitude in interpreting and applying its legislative
enactments.Ó (AOB, p. 33.)
There are no General Plan policies in
Woodside that can reasonably be interpreted to advocate clearing historic
structures to create open space.
To conclude that the General Plan would promote the creation of open
space through the demolition of an historic structure would require a cynical
and illogical reading. Faced with
a similar assertion of the beneficial results flowing from construction over
the top of the historic Grand Central Terminal in New York City based upon the
new constructionÕs consistency with land use designations, the Supreme Court
stated:
The suggestion that the beneficial quality of
appellantsÕ proposed construction is established by the fact that the
construction would have been consistent with applicable zoning laws ignores the
development in sensibilities and ideals reflected in landmark legislation like
New York CityÕs.
(Penn Central, supra, 438 U.S. at 134.)
In Sierra Club v. Contra Costa County,
supra, 10 Cal.App.4th
at 1224, the Court of Appeal held that a statement of overriding considerations
was invalid because three of twelve asserted benefits of a project were
unsupported by substantial evidence.
The Court explained, ÒInsofar as the statement provides a written
account of the balancing process undertaken by the County it is substantively
infirm.Ó (Ibid.)
Similarly, in the present case, as WoodsideÕs Special Counsel pointed
out, Ò. . . I donÕt think thereÕs anything in this case or record that says
that demolition would give the Town any kind of economic benefit anyway.Ó (4:1297.) The Planning Director unequivocally stated that ÒStaff
does not find that the project as proposed offers any benefits that would allow
the Town Council to adopt a statement of overriding consideration.Ó
(4:1280, emphasis added.)
Two members of the public noted that Òthe Applicant failed to
substantiate any public benefit, be it aesthetic or environmental.Ó (3:1199.)
Appellant claims that Dusek v. Redevelopment Agency (1985) 173 Cal.App.3d 1029, supports its
argument. (AOB, p. 32, fn.
40.) However, this case is clearly
distinguishable. Whereas in Dusek, a redevelopment agency had to approve demolition of
a historic hotel in order to Òimprove the environmental quality of a blighted areaÓ (id. at 1038),
the Jackling House sits in one of the most highly desirable and expensive
residential areas in the country, and WoodsideÕs General Plan calls for
preservation of historic buildings.
C. WoodsideÕs Conditions of Approval Do Not Convey a Benefit Supporting Demolition.
Appellants contend that the conditions placed upon demolition somehow
convey a benefit sufficient to support a statement of overriding
considerations. (AOB, p. 31.) Rather than supporting a statement of
overriding considerations, the Òconditions" support the conclusion that
the decision of Woodside was arbitrary and capricious. For example, Woodside made a finding
that the EIR alternative to relocate the House to another site was not
feasible, and yet as a condition of approval required that efforts be made to
see if the House could be relocated to another site to a willing taker. In light of this condition, the
findings of infeasibility made by Woodside were unsupportable.
Appellants say that the conditions imposed have Òthe potential to
restore the Residence in a new location, thus meeting the objective of
protecting an historic resource. . . .Ó (AOB, p. 35.) Although the demolition permit was delayed in order to allow
relocation bids to be solicited (3:906; 4:1397), Jobs was the sole
decision-maker in determining whether or not to accept any proposals for
relocation, and after twelve months pass the relocation delay will expire. Woodside had no power to independently
evaluate the proposals, since it already had granted approval of the
demolition, and retained no ability to evaluate the feasibility of whatever
proposals might come in. Thus, Woodside has no control over the ÒconditionÓ or
its implementation.
AppellantsÕ contention that denial of a
demolition permit Òwould not save the ResidenceÓ (AOB, p. 34) is based upon a
faulty assumption that the Jackling House would be destroyed one way or
another. The premise is faulty
because denial of a demolition permit would save the Residence from immediate
demolition. Whether or not its
continued deterioration due to the elements may be preventable, at least it
would not be affirmatively and immediately demolished.
To claim that approval of demolition Òis
the most sensible, logical and practical solution to the issues raised by the Jobs
applicationÓ (AOB, p. 35) is unsupported and absurd. Woodside could have required that the property be held open
for bidding on restoration or relocation alternatives, and that only after
that process was completed and Woodside could evaluate its results would it decide whether alternatives were indeed
infeasible. Appellants again mix
apples and oranges. Woodside has failed to adopt feasible mitigations and
alternatives. The conditions of approval do not ensure that the Jackling House
will be rehabilitated either on or off-site, and Appellants cannot show that
the approval of demolition creates any significant benefit.
III. THE
Findings OF Infeasibility and Overriding
Considerations FAIL TO Disclose WOODSIDEÕS Analytic Route.
Appellants appear to argue that any
decisions of the Planning Commission or Town Council, no matter what they are,
are entitled to weight as substantial evidence because they Òare presumed to
hold their positions because of their expertise.Ó (AOB, p. 25, fn. 32.)
It need hardly be stated that the governing boards of public agencies
sometimes make decisions that are not supported by substantial evidence,
experts though they presumably may be.
(E.g., Friends of the Eel River v. Sonoma County Water Agency (2003) 108 Cal.App.4th 859, 881 [public agency
certifying legally deficient EIR]; Berkeley Keep
Jets Over the Bay Com. v. Board of Port Cmrs.
(2001) 91 Cal.App.4th 1344 [same].) The expertise of the members of a governing body does not
transform their votes upon projects into expert opinions that constitute
substantial evidence to support their decisions where such evidence is
otherwise lacking.
Despite the advice of its Planning Director and its special counsel that relocation was a feasible alternative, WoodsideÕs Town Council found that all alternatives, including relocation, were infeasible and adopted a statement of overriding considerations. However, it did not provide factual evidence to support such a conclusion, as required by Public Resources Code section 21081 and Guidelines section 15091. A public agencyÕs findings must disclose the Òanalytic routeÓ used to reach a conclusion. (Topanga Assn. for a Scenic Community v. County of Los Angeles (1974) 11 Cal. 3d 506, 515.)
Appellants profess reluctance to add to the length of their brief to argue the adequacy of the CouncilÕs findings Òas an explanation of its decision.Ó (AOB, p. 36.) But the record is not self-explanatory, and in any case the record does not show the facts and the inferences the Council relied upon to reach its conclusions about infeasibility and overriding benefits. As in Village Laguna, the CouncilÕs attempt to explain the basis of its overriding considerations
was sufficient to show which Ô[s]pecific . . . social . . . considerationsÕ the board felt made the ÔNo DevelopmentÕ alternative infeasible, but it does not constitute Ôa statement of the factsÕ supporting the finding. (Cf. Foundation for San Francisco's Architectural Heritage v. City and County of San Francisco, supra., 106 Cal.App.3d 893, 913-914.)
(Village Laguna, supra, 134 Cal.App.3d at 1034.)
IV. THE
PERMIT MUST BE SET ASIDE.
Appellants make a remarkably disdainful
argument that, even if there has been a violation of CEQA and significant
adverse effects on a historic resource will occur, the demolition of the
Jackling House should be allowed to proceed as if there were no violation. (AOB, p. 37.) In support of this position, Appellants cite Laurel Heights Improvement Assoc. v.
Regents of University of California (ÒLaurel Heights IÓ) (1988)
47 Cal.3d 376.)
The Supreme Court in Laurel Heights I only permitted a project to proceed despite
substantive inadequacies in an EIR prepared for research facility expansion
project because there was Òsubstantial evidence to support the RegentsÕ finding
that the present activities will be mitigated.Ó (Id. at
424.) Therefore, after stating ÒA
primary purpose of CEQA is to protect the environment,Ó the Supreme Court
stated Òwe believe CEQA will not be thwarted by allowing UCSF to continue its present
activities at Laurel Heights.Ó (Ibid.) In
stark contrast, in the present case, significant impacts to demolition have not
been mitigated despite the availability of feasible mitigations and
alternatives but were overridden by Woodside without substantial evidence to
support that decision. CEQAÕs
fundamental purpose of protecting the environment would be unmistakably
thwarted if, despite a violation of CEQA, the demolition permit was not set
aside.
There is an enormous difference between
the continued use of an existing building, as in Laurel Heights I, and demolition of an historic resource. The Jackling House is historically
significant and is eligible for listing on the California Register of
Historical Resources (CRHR).
(2:533) The House is an
impressive example of Spanish Colonial Revival architecture. (2:534-535.) Once demolished, the unique historic structure would be gone
forever.
Appellants
imply that the demolition of a significant historic resources is only
marginally important or barely cognizable under CEQA as they irrelevantly
assert that Òno EIR would be required to consider or evaluate any environmental impacts but for the finding that the
Residence would be eligible for listing on the CRHR. . .Ó (AOB, p. 36.) More irrelevantly, Appellants note that Òdemolition of the
Residence will cause no other adverse environmental impacts,Ó (AOB, p. 36) as
if historical resource impacts are not significant in and of themselves. Testifying in Woodside, counsel for
Jobs confirmed that part of his argument was that an ÒEIR never should have
been prepared.Ó (3:829.) However, he acknowledged there had been
a chance to appeal the decision to prepare an EIR but no appeal had been
filed. (3:830.) The applicability of CEQA and the
significance of the impact may not be challenged at this late date. (Pub. Resources Code ¤ 21167.2 [EIR conclusively valid if not challenged].) It is too late for Appellants to
question the historic significance of the Jackling House, the necessity for an
EIR to consider the feasibility of alternatives to demolition, or the
importance of historical resources in California.
Appellants
decry the issuance of a writ to ensure compliance with CEQA as accomplishing
Ònothing other than the promotion of sterile process for its own sake.Ó (AOB, p. 38.) This is nonsensical, as the survival of an historic resource
is here at stake. Compliance with CEQAÕs procedural requirements is the only
way to fulfill the Supreme CourtÕs mandate that ÒWe can and must . . . scrupulously enforce
all legislatively mandated CEQA requirements.Ó (Citizens of Goleta Valley v. Board of Supervisors (1990) 52 Cal.3d 553, 564; accord Friends of the Eel River v. Sonoma
County Water Agency (2003) 108
Cal.App.4th 859, 868.) As the Supreme Court held thirty years ago in No Oil,
Inc. v. City of Los Angeles (1974) 13
Cal.3d 68, a failure to follow CEQAÕs requirements Òwould subvert the very
purpose of the Act.Ó (Id. at
81.)
Contrary to AppellantsÕ characterization
of giving Jobs, who has no interest in preserving the Jackling House, the sole
ability to evaluate the proposals that are received in response to the
short-term relocation outreach process required as a condition of approval as
Òthe best equitable compromiseÓ or the Òbest practical chance to preserve the
ResidenceÓ (AOB, p. 38), the best
possible chance for preservation of the Jackling House is if CEQA is
scrupulously observed and the demolition permit is denied. The San Mateo
Superior Court correctly determined that the approval of the demolition permit
was unlawful because it will have a significant environmental impact, there are
feasible mitigations and alternatives, and there are no overriding public
benefits to demolition.
Only by requiring the [sponsoring agency] to fully
comply with the letter of the law can a subversion of the important public
purposes of CEQA be avoided, and only by this process will the public be able
to determine the environmental and economic values of their elected and
appointed officials, thus allowing for appropriate action come election day should a majority of the voters
disagree.
(People v. County of Kern (1974) 39 Cal.App.3d 830, 842.)
Since Woodside has failed to proceed in a
manner required by law, the demolition permit it approved in error must be set
aside. (Sierra Club v. County
of Napa (2004) 121 Cal.App.4th 1490,
1497.) ÒFull compliance with the letter of CEQA is essential to the maintenance
of its important public purpose.Ó (Environmental Protection Information
Center, Inc. v. Johnson (1985) 170 Cal.App.3d 604, 622.)
CONCLUSION
By approving the demolition of the historic Jackling House when the EIR process identified feasible alternatives and the record contains no substantial evidence that all alternatives are infeasible or that the benefits of the project outweighed the significant impacts, Woodside has abused its
discretion. The Judgment should be affirmed to uphold the integrity of CEQA and to prevent the loss of the Jackling House.
DATED: July __, 2006 Respectfully Submitted,
CHATTEN-BROWN & CARSTENS
By: _____________________________
Douglas P. Carstens,
Attorneys for Respondent,
UPHOLD OUR HERITAGE
CERTIFICATE OF WORD COUNT
[California Rules
of Court, Rule 14(c)]
I,
Douglas P. Carstens, counsel for Respondent, UPHOLD OUR HERITAGE, certify that
the total word count of this brief, including footnotes, but excluding this
certificate and the Tables of Contents and Authorities, is _______words. I am relying on the word count of the
Microsoft Word program on which this brief was prepared in making this
determination.
Dated:
July __, 2006 _________________________________
DOUGLAS P. CARSTENS
F:\Woodside\Pleadings\Appeal\Finals\Opposition
fnl.doc
[1] Though designated as an alternative in the EIR,
moving the Jackling House off-site is really a mitigation measure for the
project. The Supreme Court noted
that alternatives Òare a type of mitigation.Ó (Laurel Heights
Improvement Assoc. v. Regents of University of California (1988) 47 Cal.3d 376, 403.) For
simplicity, Respondent will refer to the preservation options as ÒalternativesÓ
rather than alternatives and mitigation measures.
[2] While review is de novo, Respondent references the well-reasoned decision of
Judge Weiner for its objective and comprehensive explication of the factual and
legal issues in light of the whole record. Appellants go too far in arguing that the reasoning by which
the trial court reached its conclusions Òshould be irrelevantÓ. (AOB, p. 14.) Treating de novo review as if the trial court's ruling in a CEQA case is merely a ticket
of admission to the Court of Appeal improperly denigrates the trial courtÕs
role. (See Koster v. County
of San Joaquin (1996) 47 Cal.App.4th 29,
44-45 [Òin many [CEQA] cases, trial courts provide us with a thorough written
opinion which helps to clarify issues for appealÓ].)
[3] Preservation Action Council of San Jose v. City of
San Jose, County of Santa Clara
Superior Court case number 1-04-CV-012829 (Honorable Leslie C. Nichols
presiding).The case is currently on appeal in the Sixth District Court of
Appeal, case number H028201 and was heard on June 12, 2006. The TownÕs Special Counsel put the case
into the record (4:1283) and it is included in the joint appendix. (JA 157-180.)
[4] A copy of this slip opinion is concurrently lodged.
[5] Erickson
involved efforts to preserve the so-called Red Wing
Irish Row Houses pursuant to Minnesota's Environmental Rights statute. Interestingly, despite the statement
cited by Appellants, the Court in Erickson found that an injunction to prevent demolition was properly issued
because of the historic value of the property.
[6] The
Supreme Court recently reaffirmed the validity of Penn CentralÕs analysis.
(Tahoe-Sierra Preservation Council, Inc. v. Tahoe Regional Planning
Agency (2002) 535 U.S. 302,
315.)
[7] In Benenson
v. U.S. (1977) 548 F. 2d 939, the Court of Claims found that the governmental action designed
to prevent demolition of the Willard Hotel in Washington, D.C. so as to
facilitate acquisition constituted a taking. Attempts by the owner to seek
approval for new uses were frustrated because of the government's desire to
acquire the property.